Fervo now has $12B in orders for its geothermal power tech
Summary
- Fervo reported $11.9 billion in contracted revenue for the third quarter, an increase from $7.2 billion in the previous quarter.
- The company completed its first 100 megawatt power plant at Cape Station in Utah earlier this year.
- Fervo is on track to complete a 396 megawatt plant for Google by the end of 2028 at the same Utah site.
- Experts initially estimated the Cape Station site could produce 4 gigawatts, but it now has the potential to generate 8.4 gigawatts.
- The Google project, renamed Cape Google 400, allows Google to draw power or sell excess electricity to other customers.
- Construction occurs on Fervo's schedule while Google develops data centers on its own timeline, avoiding mutual delays.
- Newer wells at the site are deeper & hotter, with each capable of generating 15 megawatts gross power.
- Recent GeoBlocks link multiple wells to generate 50 megawatts, sized to match typical data center hall demand.
- Fervo ended the quarter with an operating loss of $43.7 million, $1.9 billion in cash & cash equivalents, & $301.6 million in long-term debt.
- The first phase of Cape Station cost $7,000 per kilowatt of capacity, while the Google project cost $5,500 per kilowatt.
- With subsidies, the Google project cost is equivalent to a natural gas plant running on fuel costing $6 per million BTUs.
- Fervo aims to reach a long-term target of $3,000 per kilowatt to significantly undercut natural gas power prices.
Geothermal company Fervo is targeting natural gas as it brings down geothermal drilling costs at its 8.4 GW resource in Utah.