Province says new data centre policies will address Albertans’ concern over growing industry

Summary

  • Alberta introduced omnibus Bill 42 to restrict data centres 10 MW or larger from being built within 600 metres of homes or on high-quality farmland.
  • The new policies prohibit such facilities on irrigated land to protect approximately 14 million acres of Class 1 \& 2 agricultural land.
  • These measures respond to public backlash over the rejected 1.4 GW Synapse project in Olds by preventing similar large-scale developments near residential areas.
  • The Alberta Utilities Commission (AUC) will regulate all data centres 10 MW or larger, enforcing noise \& light standards similar to power plants.
  • The legislation mandates the development of efficiency standards for water use \& requires large data centres to pay for necessary grid infrastructure.
  • Projects with existing approved permits are exempt from the new restrictions.
  • The province aims to address affordability concerns by having large-load users cover transmission costs, though ministers did not directly address rising electricity prices.
  • Meta's $13 billion Sturgeon County data centre, approved to draw 970 MW, remains unaffected by the new rules.
  • Approximately 30 per cent of the 70 data centres in Alberta's concierge program could be impacted if Bill 42 passes.
  • The bill includes additional changes such as increased penalties for illegal dumping, a new oil \& gas cleanup fund, expanded forest market access, \& the repeal of the unimplemented Oil Sands Emissions Limit Act.

Alberta is making changes to where some data centres can go.