Ameren Missouri updates 20-year energy roadmap to maintain and develop cost-effective energy resources to keep grid reliable for customers

  • Ameren Missouri released its 2026 Integrated Resource Plan (IRP) as a 20-year roadmap to maintain reliable service & manage costs under various customer usage scenarios.
  • The plan selects a preferred portfolio from over 20 options to optimize a mix of natural gas, solar, energy storage, fuel cells, wind, nuclear, & other technologies.
  • Natural gas capacity will expand with 2,100 MW of combined-cycle resources in service by 2031, 2,800 MW by 2035, & 1,400 MW by 2042.
  • On-demand simple-cycle natural gas generation will add 1,900 MW by 2029, with an additional 2,400 MW scheduled after 2040.
  • The plan includes adding 500 MW of natural gas fuel cells by 2030 to provide scalable, reliable energy at any time.
  • Solar generation will increase by 1,300 MW by 2030 & another 2,300 MW by 2045, complemented by 1,500 MW of wind energy after 2030.
  • Battery storage capacity will accelerate to 2,400 MW by 2030 to ensure energy availability during high-demand periods.
  • 1,200 MW of new nuclear generation is planned for 2040, with advanced large-scale reactor designs & small modular reactors under consideration.
  • Ameren Missouri expects to seek an extension to operate the Callaway Energy Center beyond 2044.
  • The utility committed to serving 2.8 gigawatts of large-load demand by 2030 through signed electric service agreements.
  • The IRP is filed with the Missouri Public Service Commission every three years & evaluates resource options using broad assumptions & scenarios.
  • The release includes extensive forward-looking statements detailing risks such as regulatory changes, cost recovery challenges, supply chain disruptions, & technological advancements.