Aston Bay Announces Pre-Feasibility Study Results and Maiden Mineral Reserve for the Storm Copper Project, Nunavut

  • Aston Bay Holdings Ltd. announced the Pre-Feasibility Study results for the Storm Copper Project on Somerset Island, Nunavut, held in a joint venture with American West Metals (80% operator interest, 20% free carried interest for Aston Bay).
  • The maiden Probable Mineral Reserve totals 12.58 Mt at 1.20% Cu grade, containing 151,400 tonnes of copper and 1.50 Moz of silver, effective 1 November 2026.
  • Base case economic metrics include an after-tax NPV7% of C$165.1 million (US$118.9 million) and an IRR of 32.8%, calculated at an assumed investment decision date of 30 September 2029.
  • Mining is scheduled for 8.6 years from January 2030 to July 2038, with processing running until April 2040, resulting in a total production life of 10.5 years.
  • Total capital costs are estimated at C$164.69 million, including C$37.90 million in pre-development capital, C$112.58 million in initial capital, and C$14.21 million in expansion capital.
  • Life-of-mine operating costs average C$72.00 per tonne processed, yielding a C1 cash cost of US$3.45/lb and an AISC of US$3.73/lb for payable copper in the base case.
  • Production will generate 688,290 dmt of concentrate averaging 14.97% Cu and 45.8 g/t Ag, with recoveries of 68.2% for copper and 67.5% for silver.
  • A binding offtake agreement with Ocean Partners covers 100% of base production, while Ocean Partners has offered up to 80% debt financing for initial capital, subject to a bankable feasibility study.
  • The project envisions a contractor-operated open-pit mine utilizing sensor-based sorting and gravity concentration, with a life-of-mine strip ratio of 5.6:1.
  • A spot price sensitivity case using current market prices shows an after-tax NPV7% of C$323.8 million and an IRR of 55.1%.
  • The PFS excludes Inferred Mineral Resources from the mine plan, treating them as waste, and relies on AACE Class 4 cost estimates with an accuracy range of −30% to +50%.
  • Environmental assessments and permitting are ongoing, with the Nunavut Impact Review Board process currently paused pending further information from the operator.
  • The project is accessed via barges, seasonal roads, and a permanent airstrip, with all power generated on-site by diesel generators.
  • Hydrogeological and permafrost studies are identified as required work for the next study stage to confirm site conditions.
  • A full Technical Report supporting the PFS will be filed on SEDAR+ within 45 days of this announcement.