Calumet Announces First Quarter 2026 Operational Update

  • Calumet Inc. announced its first quarter 2026 operational update on April 2, 2026.
  • The Shreveport facility suspended operations late in the quarter due to organic chlorides found in feedstock tanks.
  • The unplanned outage caused a production loss of approximately 750,000 barrels while an investigation into the chloride source is conducted.
  • The Shreveport facility is now fully operational \& processing over 50,000 barrels per day of feedstock following repairs \& inspections.
  • Montana Renewables' MaxSAF® expansion shutdown began the week of March 2nd \& is expected to last 48 days.
  • The Montana Renewables project is more than 70% complete \& remains on time \& on budget.
  • Calumet manufactures specialty branded products \& renewable fuels \& operates twelve facilities across North America.