E3 Lithium Completes Phase 2 of its Demonstration Facility, Commences Final Phase and Provides Regulatory Update at its Clearwater Project

  • E3 Lithium has completed Phase 2 of its Demonstration Facility at the Clearwater Project in Alberta & commenced Phase 3 operations.
  • Phase 3 involves recommissioning the 30-column Direct Lithium Extraction (DLE) system to process brine from the Leduc Reservoir into battery-grade lithium carbonate.
  • A second Phase 3 step includes engineering & operating a single scaled-up DLE column to increase processing flow rates & generate data for project financing.
  • Phase 3 serves as the final activity in the Demo program, marking the transition from technology development to commercial readiness & shovel-ready status.
  • The 30-column system targets ≥90% lithium recovery, ≥40% lithium concentration relative to impurities, ≥400 mg/L lithium concentration, & battery-grade purity (≥99.5% Li₂CO₃).
  • Phase 2 successfully produced over 80,000 m³ of brine & collected 350 samples for detailed brine chemistry analysis.
  • Phase 3 & Front-End Engineering Design (FEED) are supported by up to $36.5 million in non-repayable funding from Natural Resources Canada's Global Partnerships Initiative.
  • Engineering deliverables for the commercial facility are expected to continue into 2027 due to extended Phase 2 operations used for safety repairs & data collection.
  • The Alberta Energy Regulator has moved the D056 permit application for the Central Process Facility to a formal hearing phase.
  • Key business drivers for advancing the project include securing permits, completing a Class III cost estimate, & executing binding offtake agreements.
  • E3 Lithium holds 21.2 million tonnes of lithium carbonate equivalent (LCE) Measured & Indicated resources across its Clearwater Project & Garrington District.