Energy Vault Closes Non-Recourse Project Financing for 150 MW / 300 MWh SOSA Energy Center in Texas

  • Energy Vault Holdings announced the closing of $78 million in construction & bridge financing for the 150 MW / 300 MWh SOSA Energy Center in Madison County, Texas.
  • The bridge financing will be repaid upon completion using a committed $80 million preferred equity investment.
  • SOSA is the first asset acquired & developed under Energy Vault's Asset Vault platform & will operate in the ERCOT North market on a merchant basis.
  • Construction began in Q4 2025 with civil work completed & a substation installed, while major equipment is expected in coming months ahead of commercial operation in Q3 2027.
  • The project represents a $100 million investment expected to generate $9.3 million in tax revenue over 10 years & create 65 local jobs.
  • Energy Vault is self-performing the engineering, procurement & construction to support the project's development.