Gold Production for YE 2025 and Award of Impact Benefit Agreement ("IBA")

  • Amaroq Ltd. reported Year End 2025 gold production of ~6.6koz from its Nalunaq mine, exceeding the mid-point of its 6-7koz guidance range.
  • The company secured the final Impact Benefit Agreement (IBA) for the Nalunaq gold mine following a shutdown & restart in Q4 2025.
  • Mining & processing operations are expected to remain consistent into 2026, with Phase 2 commissioning targeted for Q2 2026 to increase the recovery factor to ~90%.
  • Production guidance & budget details for 2026 will be released in late February 2026.
  • Amaroq continues its strategy to develop a West Greenland Hub, including the Black Angel zinc-lead-silver project, while holding a portfolio of strategic metal licenses across South Greenland.