Hallador Energy Acquires 460 MW of Siemens Turbines for $350 Million, Accelerating Merom Natural Gas Generation Project

  • Hallador Energy entered an Asset Purchase Agreement with Energy World Corporation to acquire approximately 460 MW of Siemens gas turbines, generators, a steam turbine, & ancillary equipment for $350 million.
  • Total delivered costs including transportation, refurbishment, insurance, & logistics are estimated at $450 million ($760/kW purchase price plus $100 million in ancillary costs).
  • The equipment has never been fired & is being acquired to secure long-lead items in a constrained market while avoiding new turbine delivery delays.
  • The acquisition supports Hallador's proposed Merom simple cycle natural gas project currently advancing through MISO's ERAS interconnection process.
  • The facility is targeted to begin generating revenue & cash flow between late 2028 & mid-2029 upon project completion.
  • Hallador maintains no outstanding bank debt as of March 31, 2026, & holds a $120 million credit facility while pursuing project-level & structured financing.
  • The Company's contracted sales book grew to over $2.1 billion in 2026, including a 12-year capacity agreement valued at over $1 billion.
  • Hallador plans to complete the MISO ERAS study by September 2026 before making a final investment decision.
  • The Company retains optionality to advance the full project, sell the project with equipment, or sell the equipment on a standalone basis subject to regulatory & commercial milestones.
  • Hallador will host a conference call on June 2, 2026, at 8:30 a.m. Eastern Time to discuss the transaction, with details to be filed in an 8-K with the SEC.