Hallador Reports Q2 2026 Results; Gas Project Budget Reduced Below $800 Million

  • Hallador Energy Company reported Q2 2026 financial results with total revenue decreasing to $101.5 million from $102.8 million in the prior year period.
  • The company recorded a net loss of $15.2 million in Q2 2026 compared to net income of $8.2 million in the prior year period.
  • Adjusted EBITDA for the quarter was $(2.9) million, a decline from $3.4 million in the same period last year.
  • Turtle Creek Gas project commercial operation is expedited to the second half of 2028, with total project costs now expected to be below $800 million.
  • The Merom Unit 1 turbine disassembly is underway with shipments scheduled for September 2026, while the interconnection application is in MISO's ERAS process.
  • Contracted forward sales at the segment level reached $2.4 billion through 2040, including intercompany coal sales.
  • Q2 results were impacted by higher maintenance costs for Unit 1 reliability upgrades & higher purchased power costs due to unplanned downtime at Unit 2 during elevated market prices.
  • Capital expenditures for Q2 2026 totaled $26.3 million, driven by reliability upgrades & Turtle Creek project spending.
  • Hallador drew $45.0 million under its delayed draw term loan in May 2026, resulting in total bank debt of $45.0 million as of June 30, 2026.
  • Total liquidity stood at $84.2 million at the end of June 2026, up from $42.0 million in June 2025.
  • Management hosted a conference call on August 10, 2026, at 5:00 p.m. ET to discuss the financial & operational results.