Hyperscale Data Provides Update on Progress of Michigan AI Data Center; More Than $70 Million Invested in Alliance Cloud Services and the Michigan Facility

  • Hyperscale Data, Inc. expects operations under its previously announced Master Services Agreement (MSA) with a California neocloud provider to commence in November 2026.
  • The Company has invested over $70 million into Alliance Cloud Services (ACS) and the Michigan Facility development as of September 15, 2026.
  • The MSA includes an initial 20 MW of critical AI compute capacity with a 10-year term, two five-year extension options, and a potential total term of 20 years.
  • If the MSA runs for the full 20-year term, the Company expects revenue exceeding $1.2 billion.
  • The customer holds an option to increase capacity to a total of 52 MW, which could generate over $3.0 billion in revenue over the 20-year term.
  • A 52 MW deployment would utilize less than 20% of the Michigan Facility's 340 MW total potential capacity, leaving approximately 270 MW available for future projects.
  • CEO Will Horne confirmed substantial equipment acquisition and emphasized the goal of generating revenue & cash flow starting in November.
  • The Company is evaluating long-term strategies for ACS, including potential separation, an initial public offering, or a sale of the Michigan Facility.
  • Hyperscale Data anticipates the divestiture of its subsidiary Ault Capital Group (ACG) to occur in 2027 via an exchange of Series F Preferred Stock for ACG shares.