Ionic Digital Receives Base Load Provisional Classification in ERCOT’s Batch Zero Process

  • Ionic Digital received a provisional Base Load classification from ERCOT for the remaining 466 MW energization request at its Ward County campus.
  • This provisional status is subject to ERCOT's ongoing verification, audit, & final determination overseen by the Public Utility Commission of Texas.
  • Energizing this tranche will bring the Ward County campus to its full aggregate demand of 700 MW.
  • The Company targets energizing the final 466 MW tranche by the end of 2027.
  • Ionic Digital is actively participating in the ERCOT process & aligns with Governor Greg Abbott's focus on grid reliability & responsible data center development.
  • The press release includes standard forward-looking statement warnings regarding risks such as market conditions, regulatory changes, & competitive dynamics.