MISO selects consortium of Ameren, GridLiance, Dairyland, Illinois Municipal Electric Agency to deliver major grid-bolstering projects in Illinois

  • MISO selected a consortium of Ameren Transmission Company of Illinois (ATXI), GridLiance Heartland, LLC, Dairyland Power Cooperative, & Illinois Municipal Electric Agency (IMEA) to develop, build, operate, & maintain two major transmission projects.
  • ATXI & GridLiance will lead project development, while Dairyland & IMEA will own portions of both projects upon in-service.
  • The projects form a new 765-kilovolt backbone in Illinois & include the Sub T–Iowa/Illinois State Line–Woodford County (STIW) & Woodford County–Illinois/Indiana State Line (WIIL) initiatives.
  • The STIW project involves constructing two 765-kV lines spanning 149 miles from Woodford County Substation to Iowa, with an estimated cost of $940 million.
  • The WIIL project involves constructing two 765-kV lines totaling 88 miles & a new 765/345-kV substation, with an estimated cost of $718 million.
  • Ownership stakes in both projects are allocated as 43% for ATXI, 43% for GridLiance, 11% for Dairyland, & 3% for IMEA.
  • Both projects are part of MISO's Long Range Transmission Planning Tranche 2.1 Portfolio approved in December 2024.
  • Expected in-service dates for both projects are 2034, pending regulatory review & stakeholder engagement.