MISO selects consortium of Ameren, GridLiance, Dairyland to deliver foundational energy grid project in Iowa

  • MISO selected a consortium comprising Ameren Transmission Company of Illinois, GridLiance Heartland, LLC, & Dairyland Power Cooperative to develop the East Adair–Minnesota/Iowa State Line–Arbor Hill–York Avenue (EASL) transmission project in Iowa.
  • ATXI & GridLiance will lead the project & jointly own it with Dairyland once placed in service, with ownership stakes of 42.5%, 42.5%, & 15% respectively.
  • The total estimated cost for the project is approximately $1.23 billion, & it is part of MISO's Long Range Transmission Planning Tranche 2.1 Portfolio approved in December 2024.
  • Project scope includes one new 765-kV transmission line spanning 187 miles, a new 345/765-kV substation named East Adair, & two new 345-kV transmission lines totaling 22 miles.
  • The 765-kV line component has an expected in-service date of June 1, 2034, while the 345-kV component is scheduled for June 1, 2032.
  • The consortium was chosen through a competitive process based on design, execution capabilities, regulatory experience, & value for customers.
  • ATXI, GridLiance, & Dairyland were also previously selected for the Sub T–Iowa/Illinois State Line–Woodford County & Woodford County–Illinois/Indiana State Line projects within the same portfolio.