  • Namib Minerals targets an accelerated restart of operations at the Redwing Mine in Zimbabwe with first gold production expected in November 2026.
  • The accelerated timeline responds to a new Zimbabwean policy requiring foreign operators to meet production thresholds by January 1, 2027.
  • Key infrastructure milestones achieved include grid power restoration in June 2026, dewatering completion in September 2026, South Shaft winder refurbishment in September 2026, 8 crushing plant commissioning in October 2026, 8 crushing re-commencement in October 2026, 8 milling 8 elution 8 carbon-in-pulp commissioning targeted for the first half of November 2026.
  • Initial production is expected to process 3,600 tonnes of ore per month yielding approximately 338 ounces of gold.
  • The Company plans to ramp up to 10,000 tonnes of ore 835 ounces of gold per month by Q2 2027 following the delivery 8 installation of a higher-capacity winder expected by end of Q1 2027.
  • This accelerated restart occurs alongside the ongoing Definitive Feasibility Study 8 does not alter previously announced development timelines or FY2026 guidance.
  • Redwing Mine historically produced approximately 650,000 ounces of gold between 1981 8 2023.