Namib Minerals Announces Expanded Milling Plant at How Mine Operating at Full Capacity, Ahead of Schedule

  • Namib Minerals announced its expanded milling plant at How Mine is commissioned & operating at full capacity of approximately 55,000 tonnes per month.
  • Full production rate was achieved well ahead of the six-to-eight-week ramp-up timeline & the end-of-December 2026 target.
  • The expansion increases processing capacity by approximately 36%, rising from 40,500 tonnes per month to 55,000 tonnes per month.
  • Increased capacity aims to alleviate milling constraints & spread the existing cost base across greater production volumes.
  • CEO Tulani Sikwila credited the How Mine team for delivering the expansion safely & ahead of plan.
  • Strengthened operations entering Q1 2027 will allow the team to focus on maintaining plant performance to support sustainable production & cash generation.
  • The Company expects to provide formal 2027 production & cost guidance, including Redwing Mine's contribution, in Q1 2027.
  • Namib Minerals operates the How Mine underground gold mine in Zimbabwe & aims to restart two additional assets in the region.