Namib Minerals – Production and Operational Update

  • Namib Minerals provided 2025 operational guidance for its How Mine, targeting production of 24,000 to 25,000 ounces, adjusted EBITDA of $22 to $26 million, & an all-in sustaining cost of $2,700 to $2,800 per ounce.
  • The 2025 focus at How Mine involves stabilizing grade performance & completing throughput-capacity improvements while advancing early-stage restart preparation at Redwing & Mazowe Mines.
  • WSP Global Inc. was appointed to execute simultaneous SK-1300 compliant feasibility studies for Redwing & Mazowe Mines over a 12 to 18-month period.
  • Phase two of the expansion plan includes dewatering at Redwing Mine, which is scheduled to commence during the feasibility study phase & take approximately eight months, alongside surface infrastructure & power supply upgrades.
  • Upon completion of feasibility studies, the Company intends to initiate CAPEX financing for major equipment & plant components, with a preliminary funding estimate of $300 million to $400 million, predominantly allocated to Redwing Mine.
  • Namib Minerals plans to pursue a balanced funding mix including project debt, strategic partnerships, & internally-generated cash flows to minimize shareholder dilution.
  • The update includes forward-looking statements regarding future operational performance, restart timelines, & costs, noting risks such as gold price volatility, capital raising difficulties, internal control weaknesses, & political instability in Zimbabwe.