NRC Commences Readiness Assessment of Terra Innovatum’s SOLO™ Construction Permit Application (CPA)

  • The U.S. Nuclear Regulatory Commission (NRC) has established the scope, schedule, & multidisciplinary review team for the first phase of the readiness assessment of Terra Innovatum's planned SOLO™ Construction Permit Application.
  • This initial phase commenced with an entrance meeting on August 10, 2026, & is expected to continue for approximately six weeks.
  • The assessment covers the Environmental Report prepared consistent with 10 CFR Part 51 & the National Environmental Policy Act.
  • NRC staff will review nine specific chapters of the Preliminary Safety Analysis Report (PSAR), including facility details, site characteristics, reactor description, engineered safety features, radiation protection, financial qualifications, decommissioning, & uranium conversion plans.
  • A multidisciplinary NRC team from advanced reactor licensing, reactor science, engineering, environmental review, & financial assessment organizations will conduct the review.
  • The early review aims to help Terra Innovatum identify & address potential questions, information needs, & technical matters before formal submission of the Construction Permit Application.
  • Following the first phase, the NRC plans to hold an exit meeting & issue a publicly available report summarizing observations within 45 calendar days.
  • This readiness assessment is a preapplication activity & does not constitute NRC approval of the SOLO™ design or predetermine the acceptance of a future formal application.
  • The current engagement builds on preapplication interactions between Terra Innovatum & the NRC since 2025, including public meetings & submissions of white papers.