Perpetua Resources Announces Third Quarter 2026 Financial Results and Provides Project Update

  • Perpetua Resources filed its unaudited condensed consolidated financial results for the period ended September 30, 2026.
  • The Company hosted a webinar on November 17, 2026, to discuss project construction progress & recent exploration results.
  • Construction highlights include completed civil works for worker housing, foundation installation, ramped-up Burntlog Route work, & ordered long-lead powerline items.
  • The 2026 Exploration Drilling Program is complete with over 16,000 meters of core drilled, identifying new high-grade gold, antimony, & gold-tungsten zones.
  • A new Fiddle discovery south of the Yellow Pine Pit returned 109.7 meters of 3.2 g/t gold & 1.1% antimony.
  • The Clark Tunnel Fault Zone yielded near-surface high-grade gold intercepts, including 25.4 meters of 4.5 g/t gold.
  • Perpetua is finalizing documentation for a $2.9 billion senior secured loan from the U.S. EXIM bank, with closing expected in Q1 2027.
  • Unrestricted cash balances stood at $443.4 million as of September 30, 2026.
  • A mobile modular antimony processing plant was commissioned in July 2026 in partnership with Idaho National Laboratory.
  • The Company opened a community resource center in Yellow Pine, Idaho, in July 2026.
  • Perpetua reported 494,480 work hours during the first nine months of 2026 with no reportable spills or serious injuries.
  • Future activities will focus on critical path construction, equipment procurement, & announcing ongoing exploration results into 2027.