Redwing Dewatering Program On Schedule

  • Namib Minerals reports dewatering at its Redwing Mine in Zimbabwe is progressing as expected since activities commenced on January 29, 2026.
  • Approximately 544,570 cubic meters of water have been pumped since the start of the operation.
  • Water levels have declined by 21.9 meters, reaching 74.9 meters below the Redwing Shaft surface collar.
  • Current combined pumping capacity stands at approximately 640 cubic meters per hour.
  • High-capacity submersible pumps are scheduled to arrive in the coming week to further increase pumping capacity.
  • Dewatering infrastructure has operated consistently without material interruptions since January 29, 2026.
  • Redwing historically produced 650,000 ounces of gold \& currently holds 1.18 million ounces in measured \& indicated resources.
  • The company aims to restart Redwing as part of its strategy to build a scaled African gold platform alongside its existing How Mine.