RWE and KKR Join Forces to Deliver 2.8 Gigawatts of New Offshore Wind Capacity in the UK – An Investment of Around £12 Billion

  • Vanguard West and Vanguard East offshore wind farms will be fully commissioned in 2030 with a combined capacity of 2.8 GW to power approximately three million UK homes.
  • RWE & KKR have completed a 50:50 joint venture transaction, with KKR acquiring a 50% equity stake in each project.
  • The total investment for the projects & associated infrastructure is around £12 billion, supported by equity commitments from both partners.
  • Financial close has been reached for non-recourse project financing of £11.1 billion in cash facilities & £1.7 billion in ancillary facilities from 35 international banks.
  • The financing package includes a £1 billion commitment from the UK's National Wealth Fund, marking its first participation in a UK offshore wind project.
  • Each project secured a 20-year inflation-indexed Contract for Difference (CfD) at a strike price of £91.20 per megawatt hour in 2024 prices during Allocation Round 7.
  • Offshore construction is set to begin in early 2027, with foundation installation for Vanguard West planned for the first half of that year.
  • Onshore infrastructure works, including cable works & substation construction, are already well advanced.
  • The projects are located between 50 & 80 kilometres off the Norfolk coast in East Anglia.
  • UK Prime Minister Andy Burnham & Energy Secretary Miatta Fahnbulleh cited the investment as a vote of confidence in British homegrown energy, jobs creation, & energy security.