newsfilter
← Earnings
Earnings Releases·

IREN — Q1 FY27 Earnings Summary

  • Financial Performance:

    • Total revenue increased 66% sequentially to $228 million for the quarter ended September 30, 2026, compared to $137 million in the prior quarter.
    • AI Cloud revenue nearly tripled sequentially to $200 million, up from $71 million, comprising $135 million in AI Cloud Services revenue and $65 million in AI Cloud Lease revenue.
    • Bitcoin Mining revenue decreased to $28 million from $67 million in the prior quarter.
    • Net loss was $263 million, an improvement from a net loss of $684 million in the prior quarter.
    • Adjusted EBITDA increased to $66 million from $19 million, with an Adjusted EBITDA margin of 29% compared to 14% in the prior quarter.
    • Total segment gross profit (non-GAAP) increased to $182 million from $104 million.
    • AI Cloud segment gross margin was 86%, consistent with the prior quarter.
    • Revenue backlog increased 22% sequentially to $20.3 billion, with approximately two-thirds associated with investment-grade counterparties.
    • Total assets were $20.6 billion as of September 30, 2026, up from $15.8 billion in the prior quarter.
    • Net debt was $4.43 billion as of September 30, 2026, compared to $216 million in the prior quarter.
    • Cash and cash equivalents were $3.52 billion, down from $5.90 billion, while restricted cash increased to $2.26 billion from $1.72 billion.
    • Deferred revenue increased to $2.54 billion ($127 million current, $2.42 billion non-current) from $1.84 billion ($46 million current, $1.79 billion non-current).
  • Guidance and Future Outlook:

    • The company targets more than $4 billion in Annualized Run-Rate (ARR) revenue to be fully contracted and funded, with a new operational target of January 2027 (previously year-end 2026), potentially extending to February 2027 due to customer-requested design changes and supplier timing.
    • Remaining planned FY27 capital expenditure is $15 billion, expected to be funded by $9 billion in cash, committed GPU financing, and prepayments, with the remaining $6 billion subject to market conditions.
    • The company targets 0.8GW of data center capacity by the end of calendar 2027.
    • Operating ARR doubled to $1 billion during the quarter.
  • Business Segments and Product Lines:

    • AI Cloud:
      • Horizon 1 data center entered service for Microsoft with NVIDIA Exemplar status.
      • Horizon 2-4 progressed to late-stage construction.
      • 2GW Sweetwater Hub received conditional inclusion in ERCOT's Batch Zero process as base load.
      • Liquid-cooled data center construction is underway at Sweetwater 1, with new liquid-cooled centers commencing at the 100MW Mackenzie site.
      • Achieved NVIDIA Exemplar Cloud status for NVIDIA GB300 NVL72 systems at Horizon 1.
      • Advanced IREN AI Cloud with Mirantis k0rdent AI, an NVIDIA Certified Hypervisor.
      • Air-cooled retrofits continued at Childress and Mackenzie sites.
    • Bitcoin Mining:
      • Revenue declined to $28 million from $67 million in the prior quarter.
    • Development & Land:
      • Secured over 30,000 acres of land supporting over 5GW of secured power and a >35GW development pipeline.
      • Secured civil works license for 300MW development in Badajoz, Spain.
      • Early-stage development work commenced at Sweetwater 2, Kiowa, and Bundey.
    • Post-Quarter Contracts:
      • Signed an expanded contract with a Leading Frontier AI Lab.
      • Signed a five-year contract at approximately $22 million per megawatt, with 90% of associated GPU capex prepaid by the customer.
      • Signed a short-term contract at $40 million per megawatt.
      • Contracted H100 GPUs at double the previous pricing.
      • Contracted pricing rose 11% on 3-year deals and 12% on 5-year deals.
  • Market and Competitive Landscape:

    • Assets and revenue are underpinned by customer contracts with NVIDIA, Microsoft, and 13 other customers.
    • The company operates as a vertically integrated AI Cloud platform with a portfolio of land and grid-connected power in renewable-rich regions across North America, Europe, and APAC.
    • Contracted pricing trends indicate rising demand, with significant increases in per-megawatt revenue for new multi-year agreements.
  • Risks and Challenges:

    • Execution and Timing: Risks include delays in development, construction, commissioning, and delivery of contracted capacity, as well as potential cost overruns.
    • Supply Chain: Potential delays, cost increases, or supply reductions for materials and equipment, specifically GPUs, due to global supply chain constraints, tariffs, and high demand.
    • Financing: Challenges in obtaining additional capital on commercially reasonable terms to meet substantial capital needs for expansion.
    • Regulatory and Permitting: Risks related to securing permits, grid connections, and power capacity, including specific regulatory changes in Texas (ERCOT) and international jurisdictions.
    • Counterparty Risk: Exposure to customer credit risk, potential contract termination, or underperformance, particularly given significant customer concentration.
    • Asset Obsolescence: Risks regarding the useful life and obsolescence of hardware (GPUs, Bitcoin mining equipment) and potential impairment charges upon retirement.
    • Market Volatility: Risks associated with Bitcoin price fluctuations, global hashrate changes, and foreign currency exchange rates.
    • Integration: Risks related to successfully integrating recently acquired businesses (Mirantis, Nostrum Group) and achieving anticipated benefits.
  • Management Commentary and Tone:

    • Daniel Roberts, Co-Founder and Co-CEO, stated that the quarter saw Horizon 1 go into service for Microsoft, AI Cloud revenue nearly triple, and operating ARR double to $1 billion.
    • Management expressed confidence in the funding strategy, noting that the $4 billion ARR target is fully funded and that owning land, power, and data centers provides flexibility to set the pace of growth.
    • The tone reflects strong momentum in the AI Cloud segment, driven by new contracts and the progression of construction projects, despite the shift in the ARR target timeline.
  • Other Key Points:

    • Acquisitions: The company recently acquired Mirantis, Inc. and Ingenostrum, S.L. (Nostrum Group), with integration efforts ongoing.
    • Capital Raising: Proceeds from the issuance of ordinary shares were $498 million in the quarter, compared to $2.11 billion in the prior quarter.
    • Financing: Proceeds from financing facilities were $2.36 billion in the quarter.
    • Rounding Convention: Beginning Q1 FY27, the company changed its rounding convention to the nearest million dollars, which may cause minor discrepancies in totals compared to prior periods.
    • Conference Call: An audio webcast was hosted on November 5, 2026, to discuss the results.
Company
IREN LTD
Sector
Financial Services
Industry
Capital Markets