  • Completed a $64 million PIPE transaction to repay Macquarie borrowings, resulting in $187 million total cash holdings ($49 million unrestricted) and $20 million in fully collateralized debt as of October 31, 2026.
  • Power availability for TCDC Phase 1 is targeted for Q3 2027 with an initial ready-for-service date in Q4 2027, while advanced non-binding negotiations continue for lease documentation covering Phases 1 and 2.
  • Executed a 20-year PPA for 200–207 MW with Luminant/ET Services and filed air permit applications for Phase 2's 550 MW of new behind-the-meter generation in partnership with Thunderhead Energy Solutions.
  • Strategic focus remains on scaling the flagship Texas Critical Data Centers project to over 1GW capacity, utilizing a modular deployment model to serve AI training and inference workloads while minimizing transmission costs.
  • No specific revenue, earnings, or cash flow figures were disclosed for the quarter ended September 30, 2026, as the release served as a business update rather than a traditional financial report.